Completion Timeline
-
Q1 2017
Design team of ISG/Gensler and construction manager Kraus Anderson selected
-
Q2 2017
Public visioning sessions held 8 design options presented to the La Crosse Center Board
-
Q3 2017
Public meeting held to discuss 2 design options chosen by the La Crosse Center Board
-
Q4 2017
2 design options are presented to City of La Crosse Common Council
-
Q1 2018
La Crosse Center Board votes in favor of a design concept
-
Q2 2018
Design concept is vetoed by the Mayor of La Crosse
-
Q3 2018
Design team begins preparing new concepts that do not encroach on Riverside Park or exceed $42M
-
November 2018
Concept creation
-
December 2018
Public input session is held to collect feedback on new design concepts La Crosse Center Board prefers West Concept
-
January 2019
City Council approves concept design. Schematic Design begins
-
March 2019
La Crosse Center Board approves Schematic Design
-
April 2019
Design Development phase begins
-
July 2019
Construction Document phase begins
-
December 2019
Construction begins
-
March 2020
North Hall re-build begins
-
January 2021
North Hall re-build scheduled completion
-
November 2021
Construction scheduled completion